Poject Updae-February 2022
Project Progress
- Architectural designs completed
- Contracted has been awarded to well renowned and accomplished builders
- Plans submitted to local authorities are approved by TTMA
- Foundation works started
Financials
- Land – donated by Maulana Sana Ullah
- Donations – £ 80,000 of£ 400,000 has been raised
- Expenditure – The cost of building construction has been evaluatedaround £ 400,000
Risks and Issues
- None to report
Next reporting period
- June 2022
SAMR Hospital – will be a two floor hospital focusing on outpatient and day surgery services with a pharmacy and GP on site to support a mini-health care ecosystem within the locality.
Project Phases & Expected Costs
Next Project Plan Review June 2022
01
Planning Approval
Start – April 2021
End – December 2021
Duration – 9 Months
Financial – $20,000
RAG Status – Completed
02
Foundation Build
Start – January 2022
End – June 2022
Duration – 6 Months
Financial – $100,000
RAG Status – On Track
03
Phase 1
(Coutpatient Services)
Start – July 2022
End – March 2023
Duration – 9 Months
Financial – $120,000
RAG Status – Not Started
04
Phase 2
(Surgery & Facilities)
Start – April 2023
End – January 2024
Duration – 10 Months
Financial – $160,000
RAG Status – Not Started