Poject Updae-February 2022

Project Progress

  • Architectural designs completed
  • Contracted has been awarded to well renowned and accomplished builders
  • Plans submitted to local authorities are approved by TTMA
  • Foundation works started

Financials

  • Land – donated by Maulana Sana Ullah
  • Donations – £ 80,000 of£ 400,000 has been raised
  • Expenditure – The cost of building construction has been evaluatedaround £ 400,000

Risks and Issues

  • None to report

Next reporting period

  • June 2022

SAMR Hospital – will be a two floor hospital focusing on outpatient and day surgery services with a pharmacy and GP on site to support a mini-health care ecosystem within the locality.

Project Phases & Expected Costs

Next Project Plan Review June 2022

01

Planning Approval

Start – April 2021
End – December 2021
Duration – 9 Months
Financial – $20,000
RAG Status – Completed

02

Foundation Build

Start – January 2022
End – June 2022
Duration – 6 Months
Financial – $100,000
RAG Status – On Track

03

Phase 1
(Coutpatient Services)

Start – July 2022
End – March 2023
Duration – 9 Months
Financial – $120,000
RAG Status – Not Started

04

Phase 2
(Surgery & Facilities)

Start – April 2023
End – January 2024
Duration – 10 Months
Financial – $160,000
RAG Status – Not Started