Main Entrance Lobby (Reception) G/F
Covered area = 855 sft @ Rs. 12,270/sft = 10,490,850
= € 52,450
Duty Doctor Room 1st G/F
Covered area = 240sft @ Rs. 12,270/sft = 2,944,800
= € 14,720
Duty Doctor Room 2nd G/F
Covered area = 240 sft @ Rs. 12,270/sft = 2,944,800
= € 14,720
Duty Doctor Room 3rd G/F
Covered area = 240 sft @ Rs. 12,270/sft = 2,944,800
= € 14,720
Main Entrance Lobby (Reception) G/F
Covered area = 855 sft @ Rs. 12,270/sft = 10,490,850
= € 52,450
Lab & Sample Collection G/F
Covered area =187 sft @ Rs. 12,270/sft = 2,294,490
= € 11,470
Pharmacy G/F
Covered area = 314sft @ Rs. 12,270/sft = 3,852,80
= € 19,265
Prayer Room G/F
Covered area = 201 sft @ Rs. 12,270/sft = 2,466,270
= € 12,330
Children Ward G/F
Covered area = 559 sft @ Rs. 12,270/sft = 6,858,930
= € 34,300
Trauma Center G/F
Covered area = 480 sft @ Rs. 12,270/sft = 5,963,200
= € 29,800
X Room G/F
Covered area = 290 sft @ Rs. 12,270/sft = 3,558,300
= € 17,800
Project Cost Breakdown
Unit Cost in Par Rupies/GB Pund Sterling | Cost of Construction & Covered Area Calculations as Per Drawings
ECG Room G/F
Covered area =383sft @ Rs. 12,270/sft = 4,699,410
= € 23,500
Male Ward G/F
Covered area = 559sft @ Rs. 12,270/sft = 6,858,930
= € 34,300
Female Ward G/F
Covered area = 559sft @ Rs. 12,270/sft = 6,858,930
= € 34,300
Minor Operation Theatre G/F
Covered area = 297 sft @ Rs. 12,270/sft = 3,644,190
= € 18,220
Admin/ Cash Counter G/F
Covered area = 144 sft @ Rs. 12,270/sft = 1,766,880
= € 8,835
IT/Security Room 1st/F
Covered area =142 sft @ Rs. 12,270/sft = 1,742,340
= € 8,710
Conference Hall 1st /F
Covered area = 288 sft @ Rs. 12,270/sft = 2,797,560
= € 14,000
CEO Office 1st/F
Covered area = 156 sft @ Rs. 12,270/sft = 1,914,120
= € 9,570
Oxygen/(Storage Room) 1st /F
Covered area = 300 sft @ Rs. 12,270/sft = 3,681,000
= € 18,400
Total Of Above
Total Covered Area = 14,120 sft @Rs. 12,270/(€ 60)